Alt. Discription 2050 Planning Horizon Traffic Operations Interchange Year of LOS D Predicted Safety (2028-2050) Construction Potential Environmental Impacts ROW & Costs
Interchange LOS SB RTI LOS NB RTI LOS 2/3-Lane Section 4/5-Lane Section Fatal & Injury Crashes Total Crashes Duration Interchange Maintenance of Traffic Rating WAPA, Wetlands and Floodway ROW Acquisition Construction + ROW + Contingency Costs
AM / PM AM / PM AM / PM 5-Year Range 5-Year Range % Increase (+) or Decrease (-) from No Build % Increase (+) or Decrease (-) from No Build Seasons 10 – Most access 1 – Least access Potential Impacts and Acres Acres $ M
1a Compressed Diamond
I-29 Under
A / A B / B A / A 2090-2095 Beyond 2105 -19% -19% 1.5 8 (on alignment)
10 (offset)
Wetlands: 4.6 ac
Floodway: 0.08 ac
0.7 $20.5
1b Compressed Diamond
I-29 Over
A / A B / B A / A 2090-2095 Beyond 2105 -19% -19% 2.5 3 WAPA transmission lines
Wetlands: 5.7 ac
Floodway: 0.12 ac
0.4 $25
2a SPI
I-29 Under
B / B B / C - 2080-2085 2080-2090 -21% -18% 2 8 Wetlands: 2.9 ac
Floodway: 0.06 ac
0.4 $33
2b SPI
I-29 Over
B / B B / C - 2080-2085 2080-2090 -21% -18% 2.5 0 WAPA transmission lines
Wetlands: 4.4 ac
Floodway: 0.09 ac
0.4 $29.5
3a DDI
I-29 Under
B / B B / B B / B 2085-2090 Beyond 2105 -19% -16% 2 10 Wetlands: 5.8 ac
Floodway: 0.10 ac
1.5 $25.5
3b DDI
I-29 Over
B / B B / B B / B 2085-2090 Beyond 2105 -19% -16% 2.5 3 WAPA transmission lines
Wetlands: 7.0 ac
Floodway: 0.14 ac
1.5 $30
NB No Build D / D F / F A / A By Year 2050 - Baseline (154) Baseline (469) - - Wetlands: 0 ac
Floodway: 0 ac
0 0